All the data in this report is fictional. The organisation, the areas, the hazards and the values belong to no client and describe no real site.

The report below is produced by the same tool on this site, from the same calculation engines — only the data is fictional. The scores, gradings and results are computed here and now, not copied into the sample.

Sample only — fictional data

Risk register

A recorded risk assessment — based on the assessor's judgement

Site / plant
Sample Industrial Facility
Department / area
Production and warehouse (sample)
Assessed by
Safety officer (sample)
Assessment date
2026-05-14
Review date
2027-05-14
Issued on
14 May 2026

Hazards recorded

#Activity / taskHazardWho is exposedExisting controlsInitial riskAdditional controlsOwnerTarget dateResidual riskStatus
1Feeding raw material into a processing machineContact with moving parts when clearing a jamMachine operators, maintenanceFixed guarding, emergency stop, work instruction15 HighPossible × SevereEnergy isolation before clearing a jam, dedicated training, monthly guard checkMaintenance manager2026-09-305 MediumIn progress
2Moving loads in the warehouse areaForklift striking a pedestrian at a route crossingWarehouse staff, visitors, driversMarked walkways, mirrors at crossings, operator licences16 HighLikely × MajorPhysical separation on the main route, reversing alarm, external driver briefingOperations manager2026-08-318 MediumIn progress
3Electrical maintenance on the main boardElectrocution working on a circuit that was not isolatedLicensed electrician, external contractorWork by a licensed electrician only10 HighUnlikely × SevereIsolation and lock-off procedure, signage, verifying dead before startingSafety officer2026-07-155 MediumClosed
4Unloading sacks at the weighing stationBack injury from repeated manual liftingProduction staff on shiftCorrect lifting training12 HighLikely × ModerateA lift trolley at the station, a sack weight limit, task rotationProduction manager2026-10-316 MediumOpen
5Floor cleaning on the packing lineSlipping on an unmarked wet surfaceEveryone in the areaCleaning at the end of the shift8 MediumLikely × MinorTemporary signage while cleaning, slip-resistant footwear, immediate spill responseShift supervisor2026-07-314 LowClosed
6Welding during preventive maintenanceIgnition of flammable material by welding sparksThe person doing the work, nearby staffExtinguisher nearby, area cleared12 HighPossible × MajorHot work permit, fire watch, post-work watch, fire-resistant covering for openingsMaintenance manager2026-09-154 LowIn progress

How the grade is calculated: The risk score is likelihood (1–5) multiplied by severity (1–5), banded into four levels: 1–4 low, 5–9 medium, 10–16 high, 20–25 very high. The scale is this tool's convention and is not required by law; the judgement of likelihood and severity is the assessor's.

Disclaimer

This document records a risk assessment completed by the assessor. The grading of likelihood and severity is their professional judgement and is not determined by the tool. The grading scale is this tool's convention and is not required by law. The document does not replace a site visit, examination by a competent professional, an employer's duties under law, or the requirements of a competent authority.

The tool that produces this report

You can produce one of these yourself, with your own data. Everything stays in your browser.

Risk Assessment Builder

Would you like us to do this for you, on your site?

Request a risk assessment